Resolution - Civic Centers: Consider a resolution authorizing the Mayor to execute a contract with Speedcrete, Inc., for the renovation of the Avenue O sidewalks at the Lubbock Memorial Civic Center.
Item Summary
This project will provide for the removal of any remaining sidewalk quarry tile and sub-structure adjacent to Avenue O and returns along Mac Davis Lane and 9th Street, at the Lubbock Memorial Civic Center. The affected area will be replaced with a concrete walk.
 
Responses from three (3) vendors were received with their total bid amounts as listed below:
 
Contractor Bid
Speedcrete, Inc. of Lubbock, Texas $150,000
SW Contracting & Construction of Lubbock, Texas $152,514
W.R. Construction, Inc. of Lubbock, Texas $154,000
 
After review of all bids submitted, City of Lubbock staff is recommending that ITB 19-14841-FM – Avenue O Sidewalk Renovations Project be awarded to Speedcrete, Inc., with the low bid in the amount of $150,000.  Staff has determined that Speedcrete, Inc. has met all of the bidding requirements and can execute the work as described in the written specifications.
Fiscal Impact
$371,000 is appropriated in Capital Improvement Project 8629, Exterior Repair and Upgrade, with $150,000 available for this purpose.
Staff/Board Recommending
Brooke Witcher, Assistant City Manager
 

Attachments
Resolution (r) - Speedcrete
Speedcrete - Bid Form (r)
Project Summary 14841
Budget Detail
CIP Detail

AgendaQuick©2005 - 2019 Destiny Software Inc., All Rights Reserved